Milnor Orthodontics
Fort Collins, CO
Location
Fort Collins, CO
Project Size
1,100 SQ. FT.
Project Timeline
14 Days
Year Completed
2014
The Milnor Orthodontics remodel was a negotiated fast-track project consisting of an entire five-bay open operatory and business office renovation. Demolition, asbestos abatement, structural modifications, and construction were performed over the 2014 Christmas and New Year Holiday during a pre-planned fourteen calendar day practice shut-down. The project was successfully completed on time and within budget as a result of three months of pre-planning and team organization.