Periondontal & Implant Center of the Rockies
Fort Collins
Location
Fort Collins
Project Size
4,373 SQ. FT.
Project Timeline
7 months
Year Completed
March 2017
The Angie Lee Periodontics Practice was complete through a negotiated design assist approach with the owner and design team. The project design began in March 2016. Preconstruction lasted over eight months, allowing the team to design to the owner’s budget while not compromising on key components. Early subcontractor involvement helped provide an accelerated construction schedule, and competitive, transparent market pricing. Construction broke ground on September 19, 2016 and was completed by March 2017.